GENERAL INFORMATION
- Postings prior to January 1, 2005
- Buffalo Ridge Rebuild Update
- Xcel Energy OATT
- The Minnesota Energy Planning Report public presentations
- FERC Order 2004 Standards of Conduct for Transmission Providers
- Operating Guides - Northern States Power Company
- FERC Order 2004 Standards of Conduct for Transmission Providers Public Postings
- Buffalo Ridge Incremental Generation Outlet Transmission Study Meeting Notice & Materials for 1/14/2005
- Buffalo Ridge Generation Output Limit Update
- Invenergy Cannon Falls, LLC Project
- Xcel Energy Wholesale Merchant Function questions concerning MISO Transmission Service Request #75614596
- CapX 2020 Zonal Meetings Presentation
- Xcel Energy Southeast Zone Meeting Presentation
- 2005 Xcel Energy's Twin Cities Zone Meeting presentation
- Southwest Minnesota Zone Meeting- Xcel Energy presentation
- West Central Minnesota Zone Meeting- Xcel Energy presentation
- New Transmission Customer Q&A
- NWCC Midwest Transmission Workshop Presentation 6/22/2005 - NW Exploratory Study
- NWCC Midwest Transmission Workshop Presentation 6/22/2005 - Buffalo Ridge Incremental Generation Outlet Study
- SW MN Wind Project Progress Map 07/05/2005
- SW MN Wind Project Progress Update 07/12/2005
- SW MN Wind Project Progress Map 07/12/2005
- SW MN-TC EHV rpt vol 1 10-24-05
- SW MN-TC EHV rpt vol 1 11-9-05
- SW MN-TC EHV rpt vol 2 11-09-05
- St. James area study
- Xcel Energy SWMN Substation Location Information
- Southwest Mankato LLS
- Dotson study scope
- SPG_Presentation
- Xcel Energy SWMN Wind Project Update 10/16/06
- Xcel Energy SWMN Wind Project Update 11/30/06
- Xcel Energy SWMN Wind Project Update 01/04/07
- WC-Zonal meeting hand out
- Eau Claire Area Load-Serving Study
- 2007 Xcel Energy-NSP Proposed Transmission Lines
- Dotson area load serving and generation outlet study
- Small Substation Upgrade Projects
- La Crosse, New Richmond, and Eau Claire Project Updates
- NSP System Order 890 Strawman
- Xcel Energy SWMN Wind Project Update 6/5/2007
- MB SPG Meeting - Initial TLTG Summary July 6, 2007
- MB SPG Meeting - RIGO Study July 11, 2007
- Notice of Intent to Submit Rate Filing.doc
- Xcel Energy SWMN Wind Project Update 09/20/2007
- Outer Metro 115 kV development plan
- NEW - 10/1/07: Attachment O - NSP formula rate to be effective January 1, 2008 through December 31, 2008
- Customer meeting on 10/11/07 to discuss 2008 Attachment O - NSP Cost Projections and Revenue Requirement Calculation
- MB Meeting 10/3/2007 - RIGO Update
- October 11, 2007 NSP MISO Attachment O - Meeting Notes
- Xcel Energy SWMN Wind Project Update 10/25/2007
- NSP Transmission Budget Forecast 11/26/07
- Outer Metro 115 kV development study- Draft 11/28/07
- Addendum for OMTP 11/28/07
- Xcel_NSP_SWMN_OASIS_Posting_2007.11.30
- Xcel Energy NSP SWMN Wind Project Update 12/6/2007
- Xcel Energy NSP SWMN Wind Project Update 12/21/2007
- G692 Interconnection Study Report
- Xcel Energy Buffalo Ridge Incremental Generation Outlet (BRIGO) Posting 04/01/08
- Xcel Energy NSP SWMN Wind Project Update 04/03/2008
- NSP Proposed Next Wind Transmission Development 04/23/2008
- 825 Wind Final Update
- July2008_SPG presentation
- North Mankato 115 kv plan
- NSP Attachment O Update - Effective January 1, 2009 to December 31, 2009
- NSP Attachment O Workpapers - 2009 Actuals Rev 4
- RIGO Final Study Report
- XEL Companies 5-Year Transmission Budget Forecast Sept. 30 2008
- Nov. 2008 SPG 10 year plan update
- NSP Attachment O for 2008 with Actual Costs
- Monticello-Fargo 345 kV Line Update Presentation
- Dotson Area Load Serving and Generation Outlet Study
- NSP Attachment O Updated - Effective January 1, 2010 to December 31, 2010
- NSP Attachement GG Updated - Effective January 1, 2010 to December 31, 2010
- NSP Project Update Report - Shared Projects for Attachment GG
- NSP 10-Year Transmission Plan and Assessment
- Wisconsin Transmission Development Plans 2010
- NSP MISO Attachment O 2009 Actuals and Supporting Workpapers Rev 3
- NSP Attachment O for 2009 with Actual Costs Rev 4
- NSP Attachment GG 2009 True-up Notice
- NSP Companies Attachment O and Attachment GG Effective January 1, 2011 to December 31, 2011
- Hollydale Project
- Park Falls Bio-Refinery
- NSP MISO Workpapers 2011 - Budget Combined
- Stone Lake - Radisson
- NSP Companies_Attachment O 2010 Actuals and Supporting Workpapers
- NSP Attachment GG 2010 True Up Notice
- NSP MISO Workpapers 2011 - Budget Combined
- NSP Companies Attachment O, Attachment GG, and Attachment MM Effective January 1,2012 to December 31, 2012
- NSP Attachment O Workpapers 2012
Link to posting of CapX 2020 5-10-05 Technical Update
The CapX 2020 Technical Update 5-10-05 will be posted on 5-12-05 on the CapX 2020 website: www.capx2020.com
Glencoe area topology change Information
The 69kV branch from Glencoe Municipal to Biscay Junction should be modeled as normally opened once the a 115kV source has been built from McLeod substation to Glencoe Municipal. This correction has been made to the MAPP 2004 series but will need to be made to cases from previous series.
Xcel Energy transmission personnel provided the markets personnel copies of the attachment. All of the information in the attachment was gleaned from interconnection studies that have been published via MISO.
 |
| TRANSMISSION SERVICES
|
 |
ANCILLARY SERVICES
|
 |
| MISCELLANEOUS
|
 |
MESSAGES
|
 |
| PROVIDER MAINTENANCE |
|
|
|